on 11-07-2008 5:48 AM
Hello Guru,
When we create a QN from a inspection lot 80000031230 the material document we canu2019t modify the material doc, before the change of release It was possible.
For example this inspection lot was created from a stock transfer.
How this happen? what should we do to make it possible to be change? the ,material document is gray out.
Hi,
which notication are you using?
Regards,
Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello,
Am using QA11, input the inspection lot created when we do MB1B movement 322, which move a stock from unrestricted to QI. Then after inputting the inspection lot via QA11, we click the tab with red flag defects, then inidcate the Code group and the code after that we click the tab NOTIFICATIOn with the pencil icon, there the Inspection lot and the material document was indicated automatic and was gray out and impossible to change.
is this standard? why this was fixed and cannot be change?
Thanks
Hi Ryan,
Whn u are creating notification through inspection lot this inspection lot will get copied and the material doc for which this inspection lot is generated ( incase of stock transfer). So it will be alyas grey in notification screen.
And secondly when you r creating notification throuh inspection lot what is the purpose for changing this inspection lot.
If u want to create notifiacton for inspection lot of ur choice use transcatio code QM01 where u can enter inpection lot as per ur requirement.
Revert if not clear
Amol
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.