Hi All,

I tried scheduling the report(HRALXSYNC)as background job.The job run was however successful.

But on checking for few user's the data are not synchronized properly.What could be the reason?

However I tried to debug the report,there were no data present to process it.Not sure what I am missing.

On Debugging the background job

On Checking for one particular user after the background job..still synch issue exist.

Table:T77SO

job.jpg (116.6 kB)
valuenotpresent.jpg (173.5 kB)
hrprog.jpg (84.9 kB)
hrprog.jpg (84.9 kB)
valuenotpresent.jpg (173.5 kB)
synch11.jpg (101.1 kB)
synch.jpg (106.7 kB)
tables.jpg (188.4 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 02 at 10:45 AM

    Hello,

    First I recommend you to check if the organization have a valid address with e-mail where the user is assigned.

    You can check KBA: 2008038 regarding to the error: "Determinations of connection to object 'S' of 'CP' XXX failed

    It contains some checks that you should perform.

    Check also the implementation of HRALX_HRALXSYNC_BADI. It can have only one active SRM implementation.

    You can also debug the consistency check with USERS_GEN in SRM to find out why the error occurs:

    Debugging hints for the users_gen transaction - https://wiki.scn.sap.com/wiki/x/rIf_Eg


    Best regards,

    Daniel