Skip to Content
0
Former Member
Nov 06, 2008 at 01:51 AM

CJ34 Budget Transfer

210 Views

- I have my projects / WBSs assigned to IM positions. I would like to know if I could still use CJ34 for transfer budget for the below scenarios:

a). transfer of budget among different WBS elements within the same project

b). transfer of budget among WBS elements of DIFFERENT projects under the same IM position

c). transfer of budget among WBS elements of DIFFERENT projects under DIFFERENT IM position

Let say my project / WBSs are NOT assigned to IM positions. Can I have budget transfer within the same project for WBS element (under different hierarchy) at any level or it has to be at the same level?

Example:

Level 1 aaaa.0001

Level 2 aaaa.0001.01

Level 3 aaaa.0001.01.01

Level 3 aaaa.0001.01.02

Level 2 aaaa.0001.02

Level 3 aaaa.0001.02.01

Level 3 aaaa.0001.02.02

a). Level 3 aaaa.0001.02.01 transfer to Level 2 aaaa.0001.01  possible?

b). Level 2 aaaa.0001.01 transfer to Level 3 aaaa.0001.02.01  possible?

Let say my project / WBSs are NOT assigned to IM positions. Can I have budget transfer for different projects for WBS element at any level or it has to be at the same level?

Example:

Project A

Level 1 aaaa.0001

Level 2 aaaa.0001.01

Level 3 aaaa.0001.01.01

Level 3 aaaa.0001.01.02

Level 2 aaaa.0001.02

Level 3 aaaa.0001.02.01

Level 3 aaaa.0001.02.02

Project B

Level 1 bbbb.0001

Level 2 bbbb.0001.01

Level 3 bbbb.0001.01.01

Level 3 bbbb.0001.01.02

Level 2 bbbb.0001.02

Level 3 bbbb.0001.02.01

Level 3 bbbb.0001.02.02

a) Level 1 aaaa.0001 transfer to Level 1 bbbb.0001  possible?

b) Level 1 bbbb.0001 transfer to Level 3 bbbb.0001.01.01  possible?

c) Level 1 aaaa.0001 transfer to Level 2 bbbb.0001.01  possible?

d) Level 3 bbbb.0001.01.01 transfer to Level 1 aaaa.0001  possible?

e) Level 3 bbbb.0001.01.01 transfer to Level 2 aaaa.0001.02  possible?