BOM Transfer

Hi,

I am Transferring BOM to the project CN33, while saving the tranasfer - instead of Reservation for WBS - PR's are getting generated for all the items though it is stock item.

in selection parameters i have selected Prelimininary Req.( to avoid requirement doubling), Multilevel ( BOM Explosion), project Stock 1

Please Do suggest

Venkatesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Nov 05, 2008 at 11:06 AM

    check your configuration of procurement indicator OPS8 it must be set to reservation for WBS

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 24, 2011 at 10:56 AM

    .

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 26, 2011 at 05:01 AM

    hi Venketsh,

    Since you have selecte preliminary reqts, system is genrateing PRs' although those are stock items. If you want to genreate resrevation for wbs only then remove prel.req. tick and transfer the BOM.