Skip to Content
avatar image
Former Member

HCI DS to IBP data load error - "Unable to process manifest file"

Hi,

We are testing the data load from file to IBP tables using HCI DS.

We are getting an error in the job execution.

The error comes in the post-processing step after the successful completion of the dataflow execution in HCI DS.

Following are few snapshots pertaining to the error.

HCI DS Trace log snapshot

HCI DS Error log snapshot

IBP Data Integration Section Rejection Report

Kindly see if we can get some pointers pertaining to the reason of the error.

Thank you.

Add comment
10|10000 characters needed characters exceeded

  • Former Member

    Hi,

    we are also facing the same issue, may i know how this error solved?

    I have verified the tables, we are using right target table to receive the data in IBP.

    Thanks,

    Srinivasa

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Nov 05, 2016 at 12:06 AM

    Hi ,

    You can verify if the correct file path is provided under directory.

    Review the below link if its due to table type

    https://archive.sap.com/discussions/thread/3872342

    Thanks, Nikhil