Skip to Content
-2

Different logical systems for project definition error in inbound IDOC

Apr 30 at 07:47 PM

53

avatar image

Hi,

I am getting this error while assigning IDOC-SDATA to structure E1BP2054_PROJDEFINITION.

even though idoc-sdata does not contain logical system name still segment structure is filled with logical system name.

idoc-sdata contains below data.

(C08400 LR - D7A L560 SVO 18MY - F&R BUMPERS LVL_CELUC 20140224TMA_DAPAN 20180430 00002738100000040091 PA000000008400EUR EUR12014022420180430 33H HUR0000001Z000001).

e1bp2054_projdefinition = idoc_data-sdata.

MOVE-CORRESPONDING e1bp2054_projdefinition TO projectdefinition.

Please suggest why this is happening. from where logical system name is coming.

Thanks,
Darshan


10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Raymond Giuseppi May 02 at 08:37 AM
0

There are a LOGSYSTEM field in E1BP2054_MASTERDATA_ALE and in E1BP2054_PROJDEFINITION, so look again.

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Hi Raymond,

Thanks for your reply.

I have solved this issue by myself.

Conversion is maintained for segment E1BP2054_PROJDEFINITION in BD55.

Due to which by default logical system name was coming in segment.

Thanks

Darshan

0

If this is resolved then please close the question (see this blog). It still shows as unanswered.

0