Hi

I have cross plant issue. Mat1 is delivered from Plant1, but getting procured from Plant2. So SPK is maintained in Plant1 for Mat1. Now when Mat1 is added into a network activity with Plant1, system created a reservation in Plant1. On MRP run system is creating PR in plant1 and not Plant2. But as I mentioned the procurement action is done in Plant2. How to do?

Pls note that when the same Mat1 is part of bom for header material in Plant1, system is creating reservation in Plant2, thus creating a PR in Plant2 by MRP run. No problem in this case.

We are using SPK as withdrawing from other plant not Stock transfer process.