Our company is planning to upgrade R/3 4.7 EXT 200 to ECC 6.0. We are planning to do the Unicode upgrade on the R/3 4.7 system then do the ECC 6.0 upgrade. Would this be an appropriate way to go about the upgrade? Has anyone done the Upgrade in this fashion, and have you experienced any big problems?

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 04, 2008 at 04:52 AM

    I would suggest to go for upgrade first and then uniocde conversion if you don't want to use CU&UC. I believe ECC 6 Uniocde conversion tools are more advanced than R/3 4.7 Unicode Conversion tools.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 03, 2008 at 09:41 PM

    I think it is a good approach, you could do it before or after but experience talks.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 15, 2009 at 04:49 AM

    Hi,

    finally which apprach you followed.

    1. CUUC

    0r

    2. Upgrade first , then unicode conversion & then UCCHECK

    or

    3. Upgrade first , UCCHECK & then then unicode conversion

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 18, 2009 at 10:39 AM

    Hi,

    as per my knowledge no need to do the uccheck in 4.7,in upgrade we r doing the uccheck in ecc6.0.

    Upgrade means we r installing the new software.

    The major stages of a technical upgrade can be

    1.System preparation and stack level patch upgrade u2013 Basis Team

    2.SPDD Phase u2013 ABAP and Functionals

    3.Up gradation of the system u2013 Basis Team

    4.SPAU Phase u2013 ABAP and Functionals

    5.DBACOCKPIT for indexing u2013 ABAP TEAM

    6.Issue resolution and error tracking u2013 ABAP and Functionals

    7.Z programs corrections u2013 obsolete function modules and objects

    Regards,

    Madhu

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.