CJ30 Transaction - use of Edit > Total Up (F9)

Hi,

I would like to know what is the use of "Total Up" (Edit > Total Up (F9)) in CJ30 Transaction.

Thanks!

Regards,

Vivian

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 03, 2008 at 10:59 AM

    Hi Vivian,

    In this link can you find some information about Total Up

    BR/Håkan

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 03, 2008 at 11:14 AM

    Hi ,

    TOTAL UP functionality adds up the values of child WBS element and shows it on the first WBS element. In laymans languange , it works as a calculator which adds the budget values at child WBS element and rolls up the total to the LEVEL1 WBS element.

    If there is any supplement/return/change done to the original budget, then by doing total up , you can get the correct total figures anually as well as overall also.

    It is always advisable to perform total up before copying the budget from one period to another , so that you can have correct figures.

    thanks,

    Dhruv Kumar Malhotra

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.