on 11-03-2008 7:11 AM
dear all,
Can any help me in suggesting.
Is there any MRP type where we can consider both forecasting and external requirements
Thanks
Raheem
Dear,
Please check with External requirement settings for MRP type V1 at
SPRO-PRODUCTION-MRP-MASTER DATA-CHECK MRP TYPE
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I have tried with V1 i.e copy of V1 as ZA MRP type, where i have maintained the following
Include ext. reqmts 2 External reqmts within replenishment lead
forecast based planning
Forecast ind. + Obligatory forecast
Cons. Ind. F'cast G Total consumption
MRP Ind. Forecast G Total requirements
EX:-
sales order 20
forecast 20
when mrp runs it is creating PR quantity of 20 i.e for forecast quantity only , not considering sales order quantity.
i.e PR quantity should be 40
Can you help me, if possible also provide me step-by step process
Thanks
Raheem
Dear,
Please check your Planning Horizon in T. Code :OPPQ
If the requirement element is outside this, during MRP run it will be taken into consideration since last planning run.
Use Lot size = EX .
Please read OSS note 51576 - MD01: MRP type V1/V2: reorder point w. requirements
It gives you an example and explanation also.
Regards,
R.Brahmankar
Hi,
Can you try with this settings please
MRP TYPE: V1
Lot size: HB(In this make a customization change.......T-code OMI4, go to lot size tab
in the Max stock level: change the option to Maximum stock level after covering requirement
Max stock level: enter the quantity in MRP 1 view
try this your problem will be solved
Thanks
Satya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Satya,
i have tried with the setting mentioned, here it is picking the customer oders (external requirements )+ max stock level as purchase requisition quantity.
ex:-
maximum stock level--40
forecast requitrement--45
sales order ---40
sales order --20
safety stock -4
reorder level--10
PR quantity generated is 100= sales order (4020)maximum stock level(40)
then it is not considering the forecast requirements.
but here maximum stock level we are giving manaully also??
my requirement is, it should consider forecast requiremensts+ external requirements (sales orders) as purchaser requisition quantity after mrp run.
Thanks
Raheem
Hi,
Configure a new lot size by copying HB in that you can configure, then you will get the desired result, try it and let us know
Thanks
Satya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
these are details maintained in the material master
mrp1:
MRP Type v1 forest and w. ext.
Reorder Point 10
Lot size mb montly lot size
mrp2:
Safety Stock 4
Period Indicator M
forecast
Hist. periods 2 Forecast periods 1
Forecast model G Period Indicator M
Initialization X Tracking limit 4.000
sales order 40
forecast 20
safety stock 4
plant stock 0
reorder point i have given manually as 10
after mrp run it is creating pr for 30 quantity i.e 20+10(reorder)
thanks
raheem
hi,
you are using V1 and what is the lot-size procedure, I think you can configure a new one in customization,
if you explain all the MRP VIEW SETTINGS then we can sort it out?
Thanks
Satya
Edited by: sathyanarayana naini on Nov 3, 2008 10:49 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.