Oct 31, 2008 at 10:25 AM

System not calculating the Project Work In Process

64 Views

Hi Experts..,

System did not capturing my plant cost & revenue, which I planned against WBS Element while calculating the work in process. In place of plan cost system is showing plan cost same as actual cost

*_Example for First Period: -_

Plan Cost : 120000

Plant Revenue : 200000

For 1st Period

Actual Cost : 20000

Actual Revenue : Nil

In Work in process Calculation (T. Code :KKA2) system result

Actual cost : 20000

Plan cost : 20000

Plan Revenue : 0.00

WIP : 0.00

System not capitalizing the cost as well as cost capturing the real plan cost & revenue in WIP result. I tested with Result Analysis Methods:-

01 Revenue-Based Method - With Profit Realization

02 Revenue-Based Method - Without Profit Realization if Actual Revenue < Plan Costs

03 Cost-Based POC Method

06 POC Method on Basis of Revenue Planned by Period

WIP result is same no change in all above methods. Please help me

Please do needful

Thanks