Hi everyone,

I have a situation where for a plant 1122, under plant parameter parameter"plant rescheduling" is configured to NOT consider PO's and PR's for rescheduling as per clients business. Now I have another requirement that for few materials we need system to consider "PO's and PR's for rescheduling". I tried using MRP group but couldn't control the rescheduling element. System ignores the PO/PR and creates PR whenever there is demand. Can anyone suggest me how do I override the plant parameters settings using MRP group or any other ways. Please find relevant screenshot attached. Let me know if you need more info.

Regards,

Prashant