when a new service is added in services tab automatically the work hours is calculated(Here 1440 hrs).The requirement is nullify the work hours(0 hrs).How to achieve that ? Is there any user exit for that?

PS: I'm new to SAP.

sap.png (129.6 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • May 01 at 11:30 AM

    Hi,

    The work gets calculated based on the Service Unit you have entered.

    If it is Hour / Day / Month, system calculates the work for PM03 control key.

    You can maintain service packages with other units like EA.

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • May 07 at 09:55 AM

    Hi...

    The work calculated into 1440 hours because you entry 2 Month in the bottom tab Services.

    2 Month = 60 days x 24 hours = 1440 hours.

    Regards,

    Kharisma