I have the following business scenario:
one of my operation could be done in various work centers, so in the routing I have alternative sequences created branching out and returning back to this operation, and in each sequence I've defined the work center that the operation could take place in. When I create an order CO01 I have to select one alternative which is probably schedules on. My question is, when I'm in CO11N I can only confirm the sequence selected in the order CO01 , what if maintenance occures and I want to work on the alternative sequnce 2?
Going back to the order and changing the operation list manually is not very practical.
Any better suggestions?
Please Advise.
Thank you