on 10-27-2008 10:12 AM
Hi,
My Client has done a GRN wrt a PO. The quality view was mantained for that material. So at the time of GRN the system has generated an inspection lot. But there was no Quality plan ceated for that material.The quality plan was created after processing the GRN. Now I am unable to do the User Decision and the Result Recording i.e i am unable to clear the inspection lot.
Please help me to resolve this issue. As this situation is not leting stores to issue the goods due to deficite of stock so this issue has been marked as High Priority.
Thanks
Sankha.
Hi,
go to QA02 after re-setting the sample using qac3
go to the inspection specifications tab
click the task list/spec tab and just save the lot
now go to qa33, select the lot and give the UD
Regards
Merwyn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use two steps
QAC3 - Re-set inspection lot - enter the inspection lot number and just save
QA02 - Change inspection lot - enter the inspection lot number and then assign the quality plan to the inspection lot and save
Regards
Merwyn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to QA32, here select the Inspection Lot (Status will be CRTD ) and click on "Change Inspection Lot" and under "Insp. specifications" Tab click on "Task list/spec." button and check whether it copies the Specifications. And then save the lot and check the status will turn up to "REL" of the lot.
Now go for Result Recording, UD and Stock Posting.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.