Change status of tasks from "in process" back to "released"

Hi,

cProjects gives us the following standard behaviour:

Once you set the status of a taks to "in process", you cannot switch it back to "released".

But we would like to enable that.

Does anybody have an idea?

Thanks,

Hansjörg

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Nov 05, 2008 at 09:11 AM

    Hi,

    The normal order is 'released' and then 'In Process'. If the status is released, it means the task is released for processing. After processing, Why will you release it? In case for some other requirement, you need some other status, then I think you can make use of User status. You can define your own user status and update it after 'In Process'.

    Regards,

    Harini S