Hi,

cProjects gives us the following standard behaviour:

Once you set the status of a taks to "in process", you cannot switch it back to "released".

But we would like to enable that.

Does anybody have an idea?

Thanks,

Hansjörg

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

The normal order is 'released' and then 'In Process'. If the status is released, it means the task is released for processing. After processing, Why will you release it? In case for some other requirement, you need some other status, then I think you can make use of User status. You can define your own user status and update it after 'In Process'.

Regards,