10-22-2008 7:49 PM
Hello friends,
We have our system going live. For this system would go down.
So as a part of it we have to stop all the batch Jobs, stop all the incomming IDOCS and also stop all the out goping IDOCS.
Please let me know what are the steps involved in this activity and how can this be acheived.
Ster
10-22-2008 7:59 PM
Run BTCTRNS1 to de-schedule jobs.
Run BTCTRNS2 to re-schedule jobs.
10-22-2008 7:50 PM
you already listed the activities, just stop the jobs in SM37, and check if there are any outbound or inbound partner profiles to process immediately, chaneg those to collect data/
10-22-2008 7:59 PM
Run BTCTRNS1 to de-schedule jobs.
Run BTCTRNS2 to re-schedule jobs.
10-22-2008 9:33 PM
Thanks Michael,
Do u mean to say if I run, BTCTRNS1 all the JObs will be stopped. So no need of going to SE37 and doing anything.
Again to restart just run BTCTRNS2 , nothing to be done in SE37.
In addition to the above do I need to do some thing in SE37 as well.
Please let me know.
Shreekant