Confirmation at mining

Apr 26 at 01:27 PM

44

avatar image

Hi Sir,

Please confirm how to map the following scenarios.

We have machine as a work centre and grilling is my operation in routing. During operation confirmation we required to specify that in which pot or area I have perform this activities then how to map this.

Regards,

Sun

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

Raghavendra Rao P V S Apr 27 at 06:21 AM
0

Hi

It looks like that your machine works in different parts of your mine.

If you want to capture the area that it has worked, one option why cant you enter in the free text provided at operation confirmation

Else try to have a custom table wherein you mention all teh areas of your mine and try to use screen enhancement CONFPP07


Regards

Ragahvendra

Share
10 |10000 characters needed characters left characters exceeded
Ruediger Schroedter
Apr 26 at 02:17 PM
0

Hi,

Can you narrate a little bit more on your question?

It is common that a routing has a work center, which represents a group of machines and at the time of the production order creation it is not know which actual work center will be performing the work. In that case you can change the work center during the confirmation transaction, but it may depend which confirmation transaction your are using.

Regards

Ruediger

Share
10 |10000 characters needed characters left characters exceeded
sun riser Apr 26 at 04:05 PM
0

Hi sir,

I am using a machine which is defined as a work center and during operation confirmation I required to mention that in which area this operation was carried out.

Regards,

Sun