on 04-26-2018 11:31 AM
Considering I am using the recommended configuration , how long does the import abap step take to finish when setting up IDES ?
It's been more than 24 hours and I see the installation still running at import step , without any failure.
It’s very difficult to answer it, as the hardware configuration is crucial (including disk speed, deployment option etc)
Usually it takes me around 6-12 hours and the longest part is import abap phase.
I would keep it running. You can check the processes running on OS level (look for R3load). Check the install log, you should see some changes there as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
10 | |
9 | |
8 | |
6 | |
6 | |
6 | |
5 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.