Hello All,

We have one requirement as below.

I have one material in 4 plants with same as storage location in all plants . In this scenario when i run the MRP for the plant 1 and the the requirement for that plant is some 20pcs. for that plant 1 storage location it has some 10 pcs. So at this point it will genereate the planned order for that plant. Also the other storage location has 20pcs each in its location.

We are running plant wise MRP. But my client req. is like this. when he run the MRP for the plant one with the req. for 20 pcs even though he dont has sufficient stock in his storage location. It should consider the other plant storage location also.

Is there any way to Map this scenario? Thanks in advance.

My conf. settings as below

Plant 1 storage location x stock 10pcs

Plant 2 storage location x stock 20pcs

Plant 3 storage location x stock 20pcs

Plant 4 storage location x stock 20pcs

Regards,

Ganesh