on 10-22-2008 5:19 AM
Hello All,
We have one requirement as below.
I have one material in 4 plants with same as storage location in all plants . In this scenario when i run the MRP for the plant 1 and the the requirement for that plant is some 20pcs. for that plant 1 storage location it has some 10 pcs. So at this point it will genereate the planned order for that plant. Also the other storage location has 20pcs each in its location.
We are running plant wise MRP. But my client req. is like this. when he run the MRP for the plant one with the req. for 20 pcs even though he dont has sufficient stock in his storage location. It should consider the other plant storage location also.
Is there any way to Map this scenario? Thanks in advance.
My conf. settings as below
Plant 1 storage location x stock 10pcs
Plant 2 storage location x stock 20pcs
Plant 3 storage location x stock 20pcs
Plant 4 storage location x stock 20pcs
Regards,
Ganesh
Dear,
Please try tis,
MRP = 1- exclude SL from MRP in MRP4 view, then system will not consider the stock for any caluation
SL MRP = 2- seperate MRP for SL, so that system will consider the stock and requirement for that storage location
In transaction OMIR, choose your plant & then for the storage location you want to exclude from MRP enter 1 (exclude from MRP)
Please try and come back.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
I will explain my req. again in detail
I have the four plants with different storage locations.
Plant 1 Plant 2 Plant 3 Plant 4 (Same Material is in all plants)
S1 S2 S3 S4
Normally I run the MRP for the Plant 1 is my planning plant it will check its plant 1 storage location and it generate the PR or PO if the stock is insufficient. It will not check for the other plants storage location.
MRP should check the other plant storage location also. Is there any possible way to meet this req.
Regards,
Ganesh
Hi Ganesh,
I don't think it is possible. As you know MRP is carried out plant wise.
And During MRP it will not check available stock in other plants.
But by using Special Procurement key it will generate PR for procurement of material from other plant.But in this case you want to consider all 4 plants for availability check..
Regards,
Dhaval
Hello all,
Thanks for prompt reply from all.
Yes i read the SAP help for MRP area material req. planning. And i foud the information message on that as Material requirements planning with MRP areas cannot be reversed.
It is advisible to go with this MRP area MRP? Also please give the steps followed to create the MRp area. And how this storage location is assigned to mrp area.
Because i tried to assign the storage location to mrp area it is allowing only one storage location. Any think i am missing?
Regards,
Ganesh
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.