on 10-21-2008 7:13 PM
hi please
explain step by step procedure to create MRP schedulr lines
thanks
ganesh
hi
First of all maintain MRP relevant parameters in material master
Create scheduling agreement, Maintain source list here mention agreement no and Put MRP relevance as 2
Run MRP in MD03 select schedule line option as 3
Vishal...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
1. Enter the MRP data in the MMR, enter the base unit of measure, p group, mrp group, mrp type, reorder point, mrp contoller, lot size etc...
In mrp 2 view, enter procurement type as external procurement, planned del time, gr del time...safety stock etc...
2. then maintain the schedule agreement and make it as source relevent in the source list, make the it as FIX, and MRP indicator as 2....Provide the proper validity periods in which you wanna generate the del. schedules....
3. Now maintain the single item single level planning from MD03...here enter the following details:
NETCH, 2, 3, 1, 1,1, and planning date ....
4. now see the planning file entry in MD21...
Hope it helps..
Regards
Priyanka.P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.