if the production order quantity is 1 no. and the operation goes on for 3 shifts he wants to confirm the operation at the end of each shift in percentage.

1 no. will be finshed at the end of 3 rd shift. so at the end of first shift he wants to confirm 30% at the end of 2nd shift it cud be 50%. so based on these he can track the effeciency of his operators.

is there anyway this could be achieved in standard SAP.

pls feed back

thanks

sita

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Oct 21, 2008 at 10:53 AM

    Sita,

    You wont get it in terms of percentage, but interms of time taken you can monitor. Try transaction CO19 to make a time event confirmation.

    You can first confirm do a confirmation at the start of the First shift for "Processing started", by the end of the shift you can confirm "Partial Processing" for the time used similarily you can again do a "Partial Processing" by end of 2nd shift and by the end of 3rd shift "Finish Processing.

    Regards,

    Prasobh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 21, 2008 at 10:54 AM

    Hi,

    You can use Time-Event Confirmation in CO19 for this purpose to confirm the status of operation at the end of each shift i.e Set up Start / Finish, Processing start / finish , Teardown start / finish , Partial Processing etc.

    Or

    You can opt for Progress Confirmation in CO1F to show the status of the progress of operation in the production order.

    However specifying confirmation in % as you mentioned 30 % etc. is not possible in Standard SAP as per my knowledge.

    Hope this helps.

    Regards,

    Tejas

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 21, 2008 at 10:54 AM

    Hi,

    You can do activity confirmation in tcode CO11N screen. Eventhough system will not give efficiency as a direct output.

    Regards,

    Dharma

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.