Hi SAP Gurus

While generating pt60 I have got this error.

in test run i did not get it, but in live run it came,

"No entry in table $ for key $ at $ T511K 40TETOL ### 01.1

Technical error no. 72

01.10.2008 Processing terminated for EE "

hoe do i know what is TETOL in table T511k, although i know how to create it in sm30 country gp 40.

plz help me.

Regards,

Vishwas

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

In TM04 schema for standard psr TD10.In this you find TETOL,the value maintained for this in constant table is Zero.This Zero is compared.

Check this,but I am not very sure abt it.

Regards

Answers (4)

Answers (4)

VKP
Contributor
0 Kudos

thanks

VKP
Contributor
0 Kudos

hi All,

Thanks for your quick replies,

i have maintained 2011 and 0050 IT's.

in V_T511K this is the configuration i have done

CGrpg Const. End Date Start Date Value Text

"40 TETOL 31.12.9999 01.01.1999 24,00 Time Test 2"

the error goes but i dont know if its the right thing to do and what its implications are...

can you folks help me out on this matter...

Rgds,

Vishwas

Former Member
0 Kudos

Hi,

TETOL Time Tolerance for Work End

CGrpg Const. End Date Start Date Value Text

"40 TETOL 31.12.9999 01.01.1999 24,00 Time Test 2"

Table entry is ok no problem.

Regards,

SriC

Former Member
0 Kudos

Hi

What is Time test-2

For country Grpg 10 TETOL is maintained as Zero,

On what basis we can maintain TETOL as 24

plz make me clear

thanks

sikindar_a
Active Contributor
0 Kudos

did u maintained 2010 or 0050 infotypes

Former Member
0 Kudos

Hi vishwas,

As far as i know that TETOL must be a payroll constant which u have maintained for that particular employee somewhere...but it is not reflected in T511k for country grouping 40.

try to check it again.

Regards,

Kitchlu