on 10-21-2008 9:44 AM
Hello Gurus,
When a non stock material is defined as a component of service order a requirement date is automatically determinded (RESBD-BDTER) on the current date. Does someone knows if one can be able to influence this field?
It means that I would like to be able to fill it by myself.
Kind regards
Chris
Hi,
The requirement date is calculated as follows:
1. The start date (earliest scheduled start) of the operation minus
2. The goods receipt processing time of the component and minus or plus
3. The lead time offset for the component in the order
The above values (point 2 and 3) can be adjusted to manipulate the
delivery date.
It is also possible to change this date by implementing customer
exit COZF0002.
-Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paul,
As you said "
The requirement date is calculated as follows:
1. The start date (earliest scheduled start) of the operation minus
2. The goods receipt processing time of the component and minus or plus
3. The lead time offset for the component in the order
The above values (point 2 and 3) can be adjusted to manipulate the
delivery date."
I have checked for stock & non stock item, but this calculation is not working for work orders. only i can change the date with offset. i checked material master record and change the GR processing time and planned delivery time but its not working. Do you have any idea why its not working?
Thanks.
Shahyan
Hi Tison,
I think u can change your planned delivery time in material master.Thus will meet ur requirment
Thanks
Ebin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.