I am getting error

Item WBS element XM-00008-1 b

udget almost exhausted

While i am doing budget release

1. I have created Internal activity and given 200 hours plan and 10days duration time

2. Created External service activity and planned 200000 Rs.

3. General Cost Activity and plan 100000 Rs.

In cj40 screen total planned value showed 200000 rs.

I created budget 500000 Budget

and My supplement budget 110000 Rs so total Current budget is 610000 Rs.

When i am going to release budget 350000 Rs. System throw above error.