Dear Experts,
I am getting error
Item WBS element XM-00008-1 b
udget almost exhausted
While i am doing budget release
1. I have created Internal activity and given 200 hours plan and 10days duration time
2. Created External service activity and planned 200000 Rs.
3. General Cost Activity and plan 100000 Rs.
In cj40 screen total planned value showed 200000 rs.
I created budget 500000 Budget
and My supplement budget 110000 Rs so total Current budget is 610000 Rs.
When i am going to release budget 350000 Rs. System throw above error.
Please help me come out this error