Item WBS element XM-00008-1 budget almost exhausted

Apr 27 at 05:40 PM

54

avatar image
Former Member

Dear Experts,

I am getting error

Item WBS element XM-00008-1 b

udget almost exhausted

While i am doing budget release

1. I have created Internal activity and given 200 hours plan and 10days duration time

2. Created External service activity and planned 200000 Rs.

3. General Cost Activity and plan 100000 Rs.

In cj40 screen total planned value showed 200000 rs.

I created budget 500000 Budget

and My supplement budget 110000 Rs so total Current budget is 610000 Rs.

When i am going to release budget 350000 Rs. System throw above error.

Please help me come out this error

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Maria Terence Apr 29 at 10:24 AM
0

Hi,

Have you configured the Budget profile and maintained the tolerence.

Regards

Terence

Show 2 Share
10 |10000 characters needed characters left characters exceeded
Former Member

HI Maria,


Thank for your response, I configured budget profile and Tolerance limit for my project.

0

Hi Venky,

There are lots of reason why this message is appearing. Check report S_ALR_87013558 whether the values you mentioned are appearing.

Try to reconstruct your CJEN and Check whether the issue is fixed.

Regards

Terence

0
sanjeev chauhan May 08 at 03:41 AM
0

Hi,

I can not see your error screenshot can you share once again what error through by system.

check budget profile if release check already marked tick? then system allow to release the budget.

Regards,

Sanjeev