on 10-20-2008 6:09 PM
In the standard system. we can release the production order even though we have material shortage.but my business process does not recommend that. what configuration settings I have to change
in order to stop that.
Hi,
In OPJK transaction (checking control), Select the order type for business function 2 & double click.
Here there are options for the availabilty check. Choose the appropriate setting & then create an order & check by releasnig.
Regards,
Senthilkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In availability checking control, you can control this. There is a option available for this. If material is not available, you can reject the release, or you can release or the user can decide whether we can release the order or not.
Regards,
V. Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
set the release control for the order type in spro.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.