Hello,
Have an interesting scenerio- I created a PO with freight, then did a MIGO, then a MIRO- When I got to the miro screen, the freight did not carry over. Under MIRO, I have it selected to "Goods/Service items + planned delievery selected," and my layout is "All information."
However, our MM consulant creates a PO, does MIGO, and goes to MIRO excatly the same way as I do it and his freight is carrying over. Is there any type of setting differences that would allow for him to get the freight to carry over, or is there something I'm missing?
hello+
.just tell me.
after completion of migo . one acconting docment is created.in that is the postings like that
inventory material +
gi/ir a/c
freight clearing a/c.
if is there. everthing is correct. if missing go to po in me23n see the freight condition type.
in miro
take goods receipts first then go for planned delivery cost.
if its useful award me
regards
reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do u have different vendor for frieght ....
Go to Me23n item details and select the frieght condition click details , check there is any different vendor ...is there, remove the vendor and try ..
before this you have to cancel the material doc...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hai,
The frieght condition which u have taken, for that in M/06, select accural in control data2 and enter 2 in vendor in GR.then try to do a new PO,MIGO,MIRO.
Regards,
BSK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.