Hi PP Experts,

Can anybody please explain me,

In OPJJ we have assign checking group 02-Ind.requirement with Checking rule 01,02 & 03. We assign that checking group to material master MRP 3 view.

So how do system select availability check with checking rule 02.

Edited by: Raja S on Oct 20, 2008 12:43 PM

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Oct 20, 2008 at 10:50 AM

    Dear,

    In OPJK you assigned the order type and plant to the checking rule.

    And checking group you assiged to the materail master in MRP 3 View

    So when you create the production order it use the checking group from materail master and checking rule for your plant and order type from. OPJK.

    Checking rule Specifies whether and how the system checks availability and generates requirements for materials planning

    Define Checking Group - OVZ1

    Define Checking Rule - SPRO ->Production -> Shopfloor Control ->Operations ->Avaibility Check -> Define checking Rule

    Define Scope of Check - OPJJ

    Define Checking Control - OPJK

    Hope clear to you.

    Regards,

    R.Brahmankar

    Edited by: R Brahmankar on Oct 20, 2008 4:23 PM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 20, 2008 at 10:53 AM

    Hi Raja,

    As u told, u have given checking group in our material master. In OPJJ, you combine checking group and checking rule to specify scope of check.

    In OPJK also we have to assign our checking rule, plant & order type.

    Edited by: Jeyaraman R on Oct 20, 2008 4:24 PM

    Add comment