Delivery date in me53n updated every time if make the change in iw32

Former Member
0 Kudos

i face one issue If we change or add any operation on IW32 the delivery date is automatically updated in the purchase requisition for all the items with the sy-datum ,any solution for this .

Accepted Solutions (0)

Answers (2)

Answers (2)

JL23
Active Contributor

OSS note 2343561 - Purchase Requisition created from Maintenance Order: How to change delivery date in the Requisition

explains the logic of the delivery date.

So I wonder why you actually want a different date in the requisition than calculated based on your order.

Former Member
0 Kudos

Hello ,

Thank you for the response .

In this issue

its a non stock material or service and its in IW32 operation tab .

and i need to update the delivery date .

JL23
Active Contributor
0 Kudos

you had not looked into the SAP note I gave you, correct?