Hi,

While working on PPDS In the interactive planning /SAPAPO/RRP3 - Product View for some products I can see the Plan orders with the resources name displayed in the /SAPAPO/RRP3 - Product View but for some products, Plan orders are generated but the resources names are not displayed.

All the products having PPM /PDS in APO and all the products are in-house manufacturing.

Can any one please let me know why it is happening with few products and what factors are controlling the display in the /SAPAPO/RRP3 - Product View.

Regards,

Ketan.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Oct 20, 2008 at 06:28 AM

    Dear Ketan,

    Pls check the filed "Plan Explosion" of that products in Product Master under PP/DS tab. Which option you have maintained in that field? If your product having PPM then field should contain 2 i.e Explode Production Process Model & if Product Having PDS then field should contain 5 i.e. Production Data Structure Generated from R/3.

    Hope this will help you.

    Regards

    Sujay

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Sujay,

      Thanks for the inputs.

      The Inputs given by you have been maintained in all the data.

      I have four regions (plants) with the same set of data. Out of that only one plant and that to with some specific product I am facing this problem. In other plants/ regions it is showing the resources for the plan orders.

      Regards,

      Ketan.

  • author's profile photo Former Member
    Former Member
    Posted on Oct 21, 2008 at 05:57 AM

    Please check whether all the PPM & PDS are active and assigned to Model (000- in case of Active model). This problem may occur because inactivation of PP or not assigned to model.

    Planning run is creating Planned order becuse maintained In house production in Material master but not able to reach resource and source location because PPM/PDS is not exploding.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 11, 2014 at 11:14 AM

    Hi Ketan,

    I am having the same issue.

    Can you please let me know how this issue was resolved for you ?

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.