Costing Variant

Hi PP Experts, Can anybody please tell me that where do we assign Costing Variant.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Oct 20, 2008 at 04:23 AM

    Dear,

    We assign the Costing Variant in order type dependent parameter in OPL8- costing tap

    Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 20, 2008 at 04:25 AM

    Hi,

    We assign costing variant in production order type dependenet parameters.

    Path - SPRO - Production - Shop floor control - Master data - order - define order type dependent parameters

    Tcode - OPL8

    Select plant & order type. Then in details screen select controlling tab. here we assign controlling reated details such as - costing variant planned or actual, product cost sollector etc.

    Hope this will help you

    Regards,

    Ashish