may i know what does schedule line mean in SO and PO? if no schedule line, what will be happened?

thanks

rgds

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Oct 19, 2008 at 07:33 AM

    Scheduale line in SO is used to give Delivery date and quantity. Schedual line controls,

    1 Movement Type

    2. Procurement type

    3. Relevant for planning (MRP)

    If you do not define schedule line then you can not achieve above things in SO...

    I hope this will help you,

    Thanks..

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      hi,

      does it mean if having scheduled line then the system will propose the delivery date and delivery quantity?

      if no scheduled line, then no delivery date and delivery quantity?