Hi All,

I want to know the step by step procedure to settle Prodution Order which is assigned to a WBS.

Please help.

Regards,

Vishal

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Oct 20, 2008 at 03:17 AM

    Following the procudure for settlement of Prod Order.

    1.KGI2 Overhead calculation

    2.co8b Settlement co product

    3. KKS2 Variance

    4. KO88 ACTUAL SETTLEMENT

    Venkat

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 20, 2008 at 05:06 AM

    Hi,

    After creating production order first you have to confirm it(CO15)....now check actuals in cost estimation then it should be delivered(MB31).....then teco the order in CO02.

    After these follow the steps given in above reply like KO88 etc.

    Regards

    Abhinay

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.