Hi,

i have created the order now while confirmation through cor6n the posting date is current date but the time is taling as 00.00.00 for execution start & there after execution finish time is calculated as per routing. i need the time for execution start date must be current time. if this is not possible then option 2 is execution start will be given manually & accordingly the finish time based om routing time will be get calculated.

can any one tell me how can i do this & if this realted for option 2 then field selction to be made as mandatory on the screen.

with regards,

kareena

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Oct 18, 2008 at 01:48 PM

    This proposal of date is possible in COR6 and not in COR6n.Try in COR6.