Skip to Content
avatar image
Former Member

One network header in a project

Hi ,

While using assembly processing I am generating project from sales order.but if I put second line item system triggers second network in the same project.I want to restrict by generating second network in same project.

Hw to achieve this ?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 19, 2008 at 02:32 PM

    Hi,

    Allocate the second material also to the same standard network (CN08).

    Hope this will help you.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 19, 2008 at 03:40 PM

    Hi,

    Allocate the second material also to the same standard network (CN08).

    Hope this will help you.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 20, 2008 at 07:29 AM

    Hi

    Put sd/ps indicator off in standard WBS .

    REGARDS

    SHASHANK

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 20, 2008 at 12:18 PM

    Hi,

    R u using same material twice or if u r using two diffrent KMATs in ur order and they are maintained in CN08 then it will always generate two networks as per standard SAP.

    Regards

    Abhinay

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 07, 2009 at 10:18 AM

    Used user exit in VA01 which will restrict the second material with KMPN.

    Add comment
    10|10000 characters needed characters exceeded