Skip to Content

Strategy-11

Hi

We are using strategy 11 for finished goods. The problem is i have created one manual production order without demand say for example 1000 units for october month. Now i have given the demand for november 2500 units and run the MRP. I am getting the planned order for 1500 units but i want it should created 2500.

I have made scope of check Incl.prod.order = Dont take into account.

If i go to the PIR screen and gave the demand in october month for that manual prod.order 1000 and after running MRP, system is giving the correct 2500 units.

Any config settings required?

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Oct 18, 2008 at 08:06 AM

    Hi Ganesh,

    Your system behaves properly, in case of strategy 11 SAP considers PrdOrd during MRP run. So if you have a PrdOrd of 1000 pcs and a PIR of 2500 pcs, SAP will create PldOrd of 1500 pcs during MRP run.

    http://help.sap.com/saphelp_47x200/helpdata/en/a2/4e799d927d11d1800f00c04fadcb73/frameset.htm

    However, (based on your setting) if the date of PrdOrd is before the date of PIR, it may occure that during confirmation the PIR qty won't be reduced. Please check:

    demand vs. consumption - historical data

    Regards,

    Csaba

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 18, 2008 at 10:04 AM

    Csaba,

    I dont have any MRP group for my FG. I have maintained consumption mode 2 and consumption periods are 999 days. even i am not getting.

    Add a comment
    10|10000 characters needed characters exceeded

    • Dear,

      Your order October PrdOrd 1000 pcs is completed and post to the inventory stock?

      If not then do GR for first order then run MRP again with planning mode 3.

      PrdOrd before tha due date of you PIR? I'm not sure you problem lies in this, but it can be one reason.

      Stg 11 is driven by consumption period...maintained in material mster Hence please check the consumption stg, forward period and abackword period in material mster MRP3?

      What your MD62 value right now?

      Regards,

      R.Brahmankar

  • Posted on Oct 18, 2008 at 07:22 AM

    Dear,

    You need to maintain the following master data for the finished product:

    Maintain strategy group 11 on the MRP screen.

    Set the Mixed MRP indicator to 2 on the MRP screen.

    Maintain the item category group (for example, NORM) on the Sales Organization screen.

    Maintain the Availability check field so that you perform an availability check without the replenishment lead time (checking group 02 in the standard system).

    What is the PIR requirment type... it should be "BSF" check and let me know.?

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 19, 2008 at 11:37 AM

    Dear,

    In Std SAP it is not possible. Conception indicators whatever you are maintaining in material master and MD62 are only for reducing PIR by requirement and not for RECEIPT like Production order.

    availability check what you are talking about will help only in sales order and not for net qty calculation.

    Hence if you want the production order not to be considered for net calculation, then only option is to change the std SAP logic which I will not recommend.

    But tell me why are you creating a manual order.

    As per stg 11, what you enter in PIR is the total production what is possible in that month, hence the whole logic of 11 is based on. But in your case you are assuming that PIR qty + manual production order qty is the production capacity of your plant which is not correct?

    pl come back with your purpose of manual creation of production order?

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.