hi all,

i want assigen one code to 2 plants, what is configuration step

what is the special roll in chart of a/c, document number range,

thanks in advance

milind

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hi,

how to new g/l active

follow this steps

Img - financial accounting - f.acc. global setting - ledgers - ledger - Define active non-leading leading ledgers

Define ledgers for Ge ledger accounting

regards,

ramu

Former Member
0 Kudos

hi janki ,

i see the path but not available their so what i m doing now?

Milind Patil

Former Member
0 Kudos

hi

Milind Patil

You can assign no of plants to one company code .you can follow below navigation path

--Enterprise Structure

--Assignment

--Logistics - General

--Assign plant to company code

Doubble click on assign plant to company code

Enter following entries

CO-CODE - PLANT

1000 - 1000

1000 - 1100

AND SO ON----


there is no extra settings in chart of accouts and document number ranges for assign morethan on plant to co code

REGARDS

TRINADHNAIDU.A

Former Member
0 Kudos

hi sir

actually they want profit center wise bal sheet & p&l statment, that time can we create cost center or other activities

u r answer is useful ans but some dout

thanks in advence

Former Member
0 Kudos

Hi

Through New GL activation its possible to get the B/S & P&L Statement in Profit Center wise. And Plants, create plants in Logistics and assign it to company code. Plant wise costs (Production costs) report also u can get based on your Production Planning confi.

Regards

Shammi

Former Member
0 Kudos

hi mam,

so how new g/l acivat their?