Difference b/w MD02(Single Item Multi Level) and MD03(Single Item SIngle Le

Guys,

I am trying to understand the difference b/w

1. MD02(Single Item Multi Level) and

2. MD03(Single Item SIngle Level)

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Oct 17, 2008 at 06:37 PM

    Single Item Multi Level- MD02 will explore and plan mutlilevel BOM requirment.

    http://help.sap.com/SAPHELP_470/Helpdata/EN/f4/7d2da044af11d182b40000e829fbfe/frameset.htm

    MD03(Single Item SIngle Level) will only plan requirment for the header material only , it will not generate receipt for the BOM component.

    http://help.sap.com/SAPHELP_470/Helpdata/EN/f4/7d2da044af11d182b40000e829fbfe/frameset.htm

    Manish

    Edited by: Manish Kumar Rathi on Oct 17, 2008 2:42 PM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 17, 2008 at 06:48 PM

    In single-item, multi-level planning the BOM is exploded and dependent requirements are generated for assemblies and components. To cover the dependent requirements, these components are also planned. If the components also have BOMs, these are also exploded and the components are planned. This process is repeated until all levels of the BOM are exploded and planned.

    Single-item Single level Planning only involves the planning of one individual material. Single-level means that the BOM is not exploded and that, therefore, only the level directly below the material is pl