Guys,

I am trying to understand the difference b/w

1. MD02(Single Item Multi Level) and

2. MD03(Single Item SIngle Level)

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

In single-item, multi-level planning the BOM is exploded and dependent requirements are generated for assemblies and components. To cover the dependent requirements, these components are also planned. If the components also have BOMs, these are also exploded and the components are planned. This process is repeated until all levels of the BOM are exploded and planned.

Single-item Single level Planning only involves the planning of one individual material. Single-level means that the BOM is not exploded and that, therefore, only the level directly below the material is pl

Former Member
0 Kudos

Single Item Multi Level- MD02 will explore and plan mutlilevel BOM requirment.

http://help.sap.com/SAPHELP_470/Helpdata/EN/f4/7d2da044af11d182b40000e829fbfe/frameset.htm

MD03(Single Item SIngle Level) will only plan requirment for the header material only , it will not generate receipt for the BOM component.