Planned Orders with Minimum Lot size in Make-to-Order case

Former Member
0 Kudos

Question: can the MRP-run create planned orders that respect the minimum lot size (material master), if the original independent requirements have consumption w/o assembly (MTO)?

I have noticed that the minimum lot size is ignored depending on the requirement class/type of the planned independent requirement. For example, I see that planned orders with independent requirement types VSE (of strategy 50) and VSEV (of strategy 60) do not respect the minimum lot size, until the moment that there is a customer order matching the planned order and a purchase requisition is created, respecting the lot size.

Does anybody know how to solve the problem? In our company, the created planned orders are used as a forecast to the vendors.

Therefore planned orders should consider minimum lot size.

Thank you so much!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Normally in MTO scenario, Lot for order qty lot size is used. Please explore the possibility to use this lot sizing procedure.

Regards,

V. Suresh

Answers (3)

Answers (3)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Please consider the following note, which provides the explanation about

to this behavior of the lot-size, when VSEV requirements are used:

125498 - MRP/Docu: Planning segment and lot-for-lot order quantity

The following section of the note describes your scenario in detail:

"The planned independent requirements for a material are in a separate

planning segment (planning strategy planning without final assembly,

requirements type VSE, VSEV).

You enter a rounding value or a rounding profile or an lot size that is

not exact in the material master.

Material Requirements Planning:

In Material Requirements Planning, planned orders are generated for the

planned independent requirements. The lot size settings (such as fixed

lot size or minimum lot size) are also not taken into account."

BR

Caetano

0 Kudos

Hi Caeteno. Hopefully this thread isn't too old and you get a notification from this question 🙂

I read through that Note. Where it says 'Sometimes the FLS or Min LS is required...because of the dependent requirements'. What about when it is required for accurate capacity requirements? The system will not generate accurate capacity requirements when the planned orders are lumping all of the volume into 1 planned order. If I have a monthly PIR for 100,000 lbs. but I always produce the batches in lot's of 5,000 lbs., my capacity requirements will be assuming setup of only 1 order. When in reality, when that customer order comes in for 100,000, I'm going to be setting up 20 orders...not 1. Hope this made sense. Any thoughts?

Thanks,
Kevin

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Kevin

We request our Community members to avoid posting into those very old questions that have been already accepted. Otherwise, we may get into endless questions, with several different threads under the same question.

Please open a new question with your doubts and add a reference to this question.

Regards,
Caetano

0 Kudos

Ahhh. My apologies. That makes sense. Thank you for letting me know. I opened a new question here:

https://answers.sap.com/questions/12900362/lot-sizing-procedures-with-make-to-order-and-assem.html

I would love to hear your thoughts/suggestions. I appreciate your time, sir!

Thanks!

Former Member
0 Kudos

Hi all,

I tried following settings:

Material master:

- Strategy 50 - Planning without final assembly

- Lot size EX

- Min Lot Size and Rounding Value (=200)

OMI4 customizing:

- MTO Lot Size: "1" Lot-for-Lot with rounding for lot size EX

Still the MRP run will deliver planned orders with lot size < 200.

Is there something else I could do?

Thank you in advance for the support!

Former Member
0 Kudos

Facing a simliar issue . DId you ever get a resolution to this?

former_member202528
Active Contributor
0 Kudos

I guess you must have activated the check box for Last Lot Exact for the Lot size - EX in T.code OMI4.

If so means remove this and then check with new requirements and MRP run with planning mode - 3.

BR,

Krishna

former_member184655
Active Contributor
0 Kudos

Dear Krishna,

I thought this was your query when you posted the same in MM forum

Regards

Mangalraj.S

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Make-to-order strategies should always be combined with lot-size key EX (lot-for-lot.Rounding values , minimum , maximum lot sizes, etc. should not be used. If you use they have no effect due to the make-to-order properties of these strategies.

You can have for MTO Strategy 50, at the max you can have Rounding Values.

If your requirement can be fulfilled with Rounding then you need to maintain the below settings.

Transaction : OMI4

MTO Lot Size: "1" Lot-for-Lot with rounding.

Hope it will help you.

Regards,

R.Brahmankar