In the defining checking groups we are having one calam with Availability check with cumulative, confirmed quantities, in this we ahve three options

0.No cumulation (old checking logic).

1.Cumulation of the confirmed quantities when creating and changing.

2.Cumulation of the requirement quantity when creating, no cumulation when changing.

3.Cumulation of the requirement quatity when creating, cumulation of the confirmed quantity when changing.

what is the difference in these three,

Please let us know.

Thanks

Rao

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

an

Former Member
0 Kudos

Hi,

1.Adds up when u create and change

2.When ur created its only required qnt and when u do changes it will not add.

3.When ur created its only required qnt and coformed qnt will add.

RV

Former Member
0 Kudos

Hi Venkat

Thanks for your respond, Can u give a little bit explanation regarding this above 3 u sed.