how to change the project details

Hi all,

for a project, we used wrong budget profile... we need to change it as another budget profile.. When I tried T.code: cj20n, budget profile field is in display mode...not allowing to change.... some other field are in change mode... How can I change this field...???

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 17, 2008 at 07:04 AM

    Hi,

    Make sure you r in change mode of CJ20N.

    if u r in change mode then u have to change field selection

    go to OPUJ then put ur project profile in content field.

    then tick radio button of budget profile as input.

    Regards,

    vivek Tripathi

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      You r right. Reenter budget.

      It will not impact any business value.

      SPRO->Project System->Cost->Budget->Maintain Budget profile.

      Venkat

  • avatar image
    Former Member
    Oct 17, 2008 at 06:42 AM

    Change in transaction OPUJ Budget profile as input option.

    If in ur existing profile u made changes then u can activate those changes thru CJBN by reconstructing availabilty control.

    Rgds

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      hi,,,

      I have change the screen field status for budget profile and project profile as input field in OPUJ., but only budget profile is changed, still project profile field as display mode only.. How could I change project profile field as input field....??

      thanks you

  • avatar image
    Former Member
    Oct 17, 2008 at 06:42 AM

    Hi,

    Goto OPUJ transaction and change ''Budget Profile ''as input field.

    Regards,

    Amit