Hi

I am trying to set up C-Chart for Characteristic attribute by following below given sample procedure.

I have maintained control indicator setting as shown below.

sp1-setting.jpg

But when I am assigning this sample procedure in the plan, I am getting error message like "The control chart in the sampling method does not match the insp. char.". Even I tries changing the results confirmation from Summarized to Single result recording, but without success.

Anything whihc I am missing? Please advise.

Regards,

Ponniah

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member184574
Active Contributor
0 Kudos

Hi,

You need to change the Valuation mode to SPC inspection in sampling procedure. Kindly make the change and test again.

Check the below link for Control charts generation in SAP QM.

https://blogs.sap.com/2015/06/25/control-charts-in-sap-qm/

Thanks