HI,

Iam creating sales order from X plant........n i need to Run MRP from Y plant

(X and Y plants contains same material with all parameters)..This requirment is to find the internal profit for the organisation

If u need more clarity plzz revert me back

regards

Luckky

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 17, 2008 at 05:31 AM

    Hi

    When creating a sales order instead of X plant enter Y plant & if there isnt enough stock in Y plant then the availability check will be carried out & the requirements will be passed on to the plant Y. Check the settings in your requirement type & what is the requirement class assigned to it, check in the requirement class whether requirements & availability check are checked. Check for your schedule line category whether the availability check & req are checked. If these settings are maintained, then you can see the requirements which are passed on the Y plant once the order is saved.

    Hope this may help you.

    Regards

    Aravind

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 16, 2008 at 01:08 PM

    Dear Lucky,

    this scenario will trated as a Make To Order In Depot.

    e.g., 1100 is depot as raised sales order but material will dispatch from factory let take 1000 . mrp will run in 1000

    could u confirm the scenario

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi guru,

      I tried in system....I raised SO from X plant...n iam trying to do MRP in Y plant it was not showing any requirments...(Same material mainained in Both the plants)

      Is thr any Setting for this...