How can we schedule a background job for order TECO?

Dear Experts,

Our client needs to schedule a background job for Prd order TECO. Currently COHV is being used, but it has to be done after manual selection of orders. Is it possible that we run it automatically everyday as a batch job?

Thanks,

Sachin

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Oct 16, 2008 at 07:40 AM

    Dear,

    Yes. You can schedule in the background.

    You can use transaction COHV, here in system status field select 'TECO' & then in mass process tab select 'Technically complete'.

    Then goto progam in the menu bar & choose execute in background.

    Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 16, 2008 at 07:38 AM

    Hi,

    Try with tcode CO44. With this you can do mass TECO by online. Enter the plant & select technicaly complete. Remove tick mark from test run.

    Now all the prod order will get TECO status collectively.

    Regards,

    Dharma

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks Dharma for the quick reply. May be I have put forth the question wroingly. I wanted to ask whether this mass processing transaction can be scheduled to run automatically at a specified time every day based on specific order selection criteria?

      Thanks,

      Sachin