Skip to Content
avatar image
Former Member

MRP output related issue

Hi all PP gurus,

Can you please help me out in this issue please? .

Suppose we are having one material no .XYZ.and This material is, also blocked for purchasing status 03, has no reordering point, no reservation, MRP type: ND (no material planning) AND anyhow it comes up on the MRP-run How come? Have you any idea??means suppose we check in MD04 then it is showing one PR.How?

Thanks ,

Narayan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Oct 16, 2008 at 06:36 AM

    Hi Narayan,

    May be PR is created manually, or created earlier before materials is block for procurement and MRP.

    Just check in MD05.It will saw last MRP result with date and time.

    Regards,

    Dhaval

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 16, 2008 at 06:35 AM

    Dear,

    Please run MRP again with planning mode-3 deleted and recreated and you can also do the consistency check for MRP. Then check your result.

    Also check planning file entry in MD20

    Regards,

    R.Brahmankar

    Add comment