Hi All,

I have run M R P through MD01. Planned independent requirement is of 800 units. Stock of material is 100 units then it is creating planned order of 700 units. While we want that planned order should be the same as Planned independent requirement i.e, 800 units no matter what is the stock of finished material, as we want to create production order for make to stock. How can I handle it?

Regards,

Hammad

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 16, 2008 at 04:54 AM

    Hi,

    Use strategy 11 for FG, system will not consider the existing stock. Assign Mixed MRP - 2 in MRP 3 of material master.

    Regards,

    Dharma

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 16, 2008 at 05:02 AM

    Hi,

    As Mr. Dharma said use strategy 11 (Gross requirement Planing) in MRP 3 view of Material Master.

    Or

    .

    Also try it by changing Requirement type to individual in MRP 4 view of Material Master.

    Regards,

    Dhaval