Production Order For Project with plant stock

Hi,

We have a scenario where in we are required to create a production order for a project.

But the material(raw material) is in a storage location and is a stock item. Even the header material is also a stock item and it to stored in the storage location.

But the order is to be created for Project and to be settled to the Project. Now the system is not allowing me to create the order.

The error is :

"Project does not allow make-to-order stock

Message no. CO746

Diagnosis

There is no project stock for the project.

To create a production order with reference to a WBS element the project must allow project stock to be maintained.

Procedure

You should select a project that allows project stock."

Now,

I don't want to have a project stock. How to go forward...

Regards

Pavan

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    author's profile photo
    Former Member
    Posted on Oct 15, 2008 at 05:18 PM

    Hi,

    What is the strategy you are using. If you are using strategy 20, then chnage it to 40.

    Also maintain individual/collective indicator to "1" - individual in MRP-4 view. So that when the order is created, the stock will be reserved as Q-project stock.

    thanks and regards

    Murugesan

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on May 04, 2011 at 06:25 AM

    solved