Dear Sapients,

Case: We are creating a test case using single material for which "Control code" is already maintained in material master,

But while creating PO, we yet getting a system message pop-up, HSN Code is not maintained.

And

even we tried maintaining manually in PO, but control code option is grayed out in Item detail Tab: India tab

Would any one let us know the reason for the same ? and suggest a solution for this ?

Thanx in advance

regards

Nagaraj

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Siva Prasad Vasireddy Apr 23 at 10:14 AM
0

Hi,

let me know where did you maintained the HSN code

this need to be maintained under Foriegn Trade Data

Show 3 Share
10 |10000 characters needed characters left characters exceeded

Hi Siva prasad,

We maintained it In International trade: Export, and International trade:Import

These are in Org.Views of MMR (MM01).

thank you

NSK


0

Hi,

did you maintain in foriegn trade- configuration level

0
Siva Prasad Vasireddy

Yes

Its been maintained in configuration level

0
Jürgen L Apr 23 at 10:40 AM
0

see this OSS note to know what you have to do to get the control code into the purchase order: 2474348 - GST India - Control code field value is not autopopulated from material master under INDIA tab in Purchase Order

However, I wonder what error message you get, what is the message number?