Skip to Content
avatar image
Former Member

Two PSA requests loaded with one DTP Delta

Hi,

I have an Info Package Full Upload loading data into PSA than DTP delta loads data into Infocube.

The problem is DTP is taking two PSA request and loads it into Cube as one DTP request.

There are doubled quantities in infocube.

There are 4 PSA request and DTP takes the 1st one and 3rd. Loading is once day. PSA request are removed if older that 4 days.

What shoud be done so only the newest PSA request is taken into consideration.

Thanks for help

Mariusz

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 15, 2008 at 11:59 AM

    Bach,

    Try setting the DTP to Delta and check the Option of Only Get Delta ONce - it will pick the oldest request in PSA which has not got updated in the data target.

    Arun

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 15, 2008 at 11:55 AM

    Hi,

    Go to monitor take the request and find the same request in psa.

    regards

    sivaraju

    Add comment