Inspection for material type INTR

This is a process industry scenario.I want to produce material A (HALB).

For this I am using 3 ROH x,y,z, and 1st creating intra material B.I want to generate the inspection lot for B.If B is ok,then using B,I will produce A.

In my master receipe, after confirming 5th operation(creation of intra material B), I want to generate inspection lot.

How can I map this scenario.

Please note material type for B is INTR.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Oct 15, 2008 at 01:48 PM

    Hi Sandip

    Assign Control key( which is having insp.char selected)In 5th operation of your master receipe,

    once process order released, inspection lot will be generate

    RR will be recorded against 5th operation

    Thanks

    Sami